Compressed schedules and liquidated damages have become the norm in today's construction environment. Because we put so much effort into planning our projects, we feel comfortable tackling some of the fastest most challenging time tables around. We believe a successful partner can evolve to meet any project demands.
Please take a look at some of our recent fast-track projects below. All were completed ahead of schedule.
St. Pete College Vet Tech - Our crews installed 60,000 sf of 14
inch C.I.P. decks in four 15,000 sfpours in a 4 week time frame.
This included columns & beams along with 395 tons of reinforcing.
Hilton Garden Inn - We used a truss table system t o build this 7
story hotel in 3 months. At the peak of construction we were
cycling a floor every week.
Met West - At 150 feet, these are the tallest free standing shear walls utilizing the Meva® form system in the world. There were 4 shear walls totaling 52 concrete pours. One pour was made everyday Monday through Saturday until complete. |